Compressor electrification
Replace the steam turbine of a 5 MW gas compressor with a motor and VSD: business case to grid application.
- documents
- 15
- motor
- 5.6 MW*
- simple payback
- 2.5 years*
- CO2 avoided
- 14,200 t/y*
A process gas compressor runs on a condensing steam turbine. The study replaces the turbine with a medium-voltage motor, an active front end VSD and a gearbox, fed from a new transformer in the existing transformer park.
Plexus made a feasibility package from one record: the business case, the electrical calculations and studies, specifications, the single line diagram, P&IDs, cause and effect, layout, cost and the grid application pack.
Scope
- New 20 kV feeder and 8 MVA transformer
- 6.6 kV switchgear and E-house
- 6.6 kV AFE VSD and 5.6 MW 4-pole induction motor
- Gearbox and compressor tie-in
- Grid connection application
Documents (15)
All studies are hypothetical. Values rest on a stated study basis. Each document was reviewed and scored before issue. Open items are listed as gaps.
Project management4
| Number | Title | Rev | Pages |
|---|---|---|---|
| 2605-PEI-PM-DB-001 | Design Basis | A6 | 17 |
| 2605-PEI-PM-RP-001 | Research Report | A6 | 10 |
| 2605-PEI-PM-RP-002 | Business Case | A4 | 4 |
| 2605-PEI-PM-RP-003 | Grid Application Pack | A6 | 5 |
Process2
| Number | Title | Rev | Pages |
|---|---|---|---|
| 2605-PEI-PR-DR-001 | P&IDs | A7 | 3 |
| 2605-PEI-PR-RP-001 | Process Description | A6 | 8 |
Piping and layout1
| Number | Title | Rev | Pages |
|---|---|---|---|
| 2605-PEI-PI-DR-001 | Transformer Bay Layout | A5 | 1 |
Instrumentation and control1
| Number | Title | Rev | Pages |
|---|---|---|---|
| 2605-PEI-IC-LS-001 | Cause and Effect | A6 | 6 |
Electrical6
| Number | Title | Rev | Pages |
|---|---|---|---|
| 2605-PEI-EL-CA-001 | Electrical Calculations | A6 | 7 |
| 2605-PEI-EL-CA-002 | Harmonic Protection Study | A5 | 7 |
| 2605-PEI-EL-DR-001 | SLD | A5 | 1 |
| 2605-PEI-EL-LS-001 | Cable Schedule | A4 | 5 |
| 2605-PEI-EL-SP-001 | TR 301 Specification | A5 | 11 |
| 2605-PEI-EL-SP-002 | VSD Motor Specification | A6 | 9 |
Cost estimate1
| Number | Title | Rev | Pages |
|---|---|---|---|
| 2605-PEI-CE-ES-001 | CAPEX Estimate | A5 | 7 |
Previews
Basis and results
| Compressor shaft power | 5 MW maximum, 4,500 kW average, 8,000 h/y* |
|---|---|
| Motor | 5.6 MW, 6.6 kV, 4-pole, Ex ec* |
| Transformer | 8 MVA, 20/6.9 kV, Dyn11* |
| Total installed cost | EUR 11.0 M, 25 % contingency* |
| Annual saving | EUR 4.4 M/y* |
| Energy prices | Gas 38 EUR/MWh, power 95 EUR/MWh, CO2 80 EUR/t* |
* Selected or calculated by Plexus from a stated study basis. The basis and each calculation are in the documents; no client data is behind these values.
What Plexus did
- Built the business case with energy, CO2 and payback from the record
- Ran IEC 60909 short-circuit, cable, harmonic, starting and protection calculations
- Wrote the transformer and VSD and motor specifications
- Drew the single line diagram and redrew the P&IDs for the new drive
- Made the cause and effect matrix and the grid application pack
Open gaps
- DataNo compressor OEM data. The torsional and lateral analysis of the train is a hold, and the existing discharge relief valve is expected to need replacement (allowance in the estimate).
- DataGrid data at the connection point (short-circuit power, harmonic limits) is assumed.
- DataEnergy and CO2 prices drive the payback and are assumed.
- DataSite demand with the new drive is 40.51 MW, above the 40 MW grid contract. Firm grid capacity is not confirmed, so the turbine stays until it is.
- ReviewFixes from the last review pass were not reviewed again. One higher-scored item (primary sources for key design criteria) and 16 lower-scored items are still open.