PLEXUSENGINEERING INTELLIGENCE

Compressor electrification

Replace the steam turbine of a 5 MW gas compressor with a motor and VSD: business case to grid application.

Sector
Energy transition
Location
Netherlands (hypothetical site)
Project
2605
documents
15
motor
5.6 MW*
simple payback
2.5 years*
CO2 avoided
14,200 t/y*

A process gas compressor runs on a condensing steam turbine. The study replaces the turbine with a medium-voltage motor, an active front end VSD and a gearbox, fed from a new transformer in the existing transformer park.

Plexus made a feasibility package from one record: the business case, the electrical calculations and studies, specifications, the single line diagram, P&IDs, cause and effect, layout, cost and the grid application pack.

Scope

  • New 20 kV feeder and 8 MVA transformer
  • 6.6 kV switchgear and E-house
  • 6.6 kV AFE VSD and 5.6 MW 4-pole induction motor
  • Gearbox and compressor tie-in
  • Grid connection application

Documents (15)

All studies are hypothetical. Values rest on a stated study basis. Each document was reviewed and scored before issue. Open items are listed as gaps.

Project management4
NumberTitleRevPages
2605-PEI-PM-DB-001Design BasisA617
2605-PEI-PM-RP-001Research ReportA610
2605-PEI-PM-RP-002Business CaseA44
2605-PEI-PM-RP-003Grid Application PackA65
Process2
NumberTitleRevPages
2605-PEI-PR-DR-001P&IDsA73
2605-PEI-PR-RP-001Process DescriptionA68
Piping and layout1
NumberTitleRevPages
2605-PEI-PI-DR-001Transformer Bay LayoutA51
Instrumentation and control1
NumberTitleRevPages
2605-PEI-IC-LS-001Cause and EffectA66
Electrical6
NumberTitleRevPages
2605-PEI-EL-CA-001Electrical CalculationsA67
2605-PEI-EL-CA-002Harmonic Protection StudyA57
2605-PEI-EL-DR-001SLDA51
2605-PEI-EL-LS-001Cable ScheduleA45
2605-PEI-EL-SP-001TR 301 SpecificationA511
2605-PEI-EL-SP-002VSD Motor SpecificationA69
Cost estimate1
NumberTitleRevPages
2605-PEI-CE-ES-001CAPEX EstimateA57

Previews

Basis and results

Compressor shaft power5 MW maximum, 4,500 kW average, 8,000 h/y*
Motor5.6 MW, 6.6 kV, 4-pole, Ex ec*
Transformer8 MVA, 20/6.9 kV, Dyn11*
Total installed costEUR 11.0 M, 25 % contingency*
Annual savingEUR 4.4 M/y*
Energy pricesGas 38 EUR/MWh, power 95 EUR/MWh, CO2 80 EUR/t*

* Selected or calculated by Plexus from a stated study basis. The basis and each calculation are in the documents; no client data is behind these values.

What Plexus did

  • Built the business case with energy, CO2 and payback from the record
  • Ran IEC 60909 short-circuit, cable, harmonic, starting and protection calculations
  • Wrote the transformer and VSD and motor specifications
  • Drew the single line diagram and redrew the P&IDs for the new drive
  • Made the cause and effect matrix and the grid application pack

Open gaps

Want this for your plant?

Tell us about your project in a short call.

Book a call